Questions about the world of GMAT Math from other sources and general math related questions.
cesar.rodriguez.blanco
Course Students
 
Posts: 142
Joined: Mon Nov 03, 2008 6:02 pm
 

PS:Work problem

by cesar.rodriguez.blanco Thu Aug 20, 2009 3:10 pm

I do not how to solve this problem.
Source: Beatthegmat.

Edusoft, a software firm has engaged certain number of men to finish a project in the stipulated time. But after working for 14 days, 1/4 of them have left and to complete the remaining project the remaining members have taken as many days as the initial number of men would have taken to complete the entire project. In how many days was the project completed?

A. 48 B. 60 C. 56 D. 40 E. None of these
kevinmarmstrong
Students
 
Posts: 28
Joined: Mon Feb 09, 2009 10:41 am
 

Re: PS:Work problem

by kevinmarmstrong Fri Aug 21, 2009 5:17 am

Suppose that with the n men who started, the task would be done in d days. Thus the task requires nd men-days.

After 14 days (d-14)n men-days of work remains, which will be done in d days by the 3n/4 men still on the job.

Thus n(d-14) =3nd/4 and d=56. Thus the project was completed in 14 + 56 = 70 days

You could also reason that 3/4 of the workforce would, in the time it takes the entire workforce to do the job, do 3/4 of the job. Thus 1/4 of the job was done in the first 14 days and consequently the entire job could be done by the entire workforce in 56 days. 14 + 56 = 70
Ben Ku
ManhattanGMAT Staff
 
Posts: 817
Joined: Sat Nov 03, 2007 7:49 pm
 

Re: PS:Work problem

by Ben Ku Sat Sep 26, 2009 3:09 pm

I like Kevin's response. Let me know if it's unclear or if you have additional questions. Thanks.
Ben Ku
Instructor
ManhattanGMAT